Kona Visayan Club
Home | Contact | Officers | Programs & Services

 


Cost report on Completed Cantao-an Project
Note:This email was sent Saturday, June 20, 2009 4:51 AM


HI ALL,

We have turned over the Cantao-an 3-room School Building to the Cantao-an National High School last June 10, 2009 . We take pride in completing the project on budget and on time for the school opening of the school year 2009 - 2010. The simple turn over ceremony was witnessed by no other than our main donors KONA Visayan Club President Jane Clement and KVC board member Gino Papre,  Feed the Hungry founders Pablito and Tessie Alarcon, Mayor Valdemer Chiong of Naga and his councilors, barangay captain and barangay councilors of Cantao-an, School Principal Saturnina and her teaching staff, Cantao-an folks, students , our very own RudyA, RodyF, RogerC  and CITAA board members and scholars. 

Actual cost spent for the project is P948,438.00 bargained as follows :

Contract Price for the 3 room building ....  P 780,544.00

Change orders during the construction ---  P   66,851.00

                      -------------------------------------------------------------------

SUBTOTAL  - - - - - - - - - - - - - - - - - - - - - P 847,395.00

LESS ADJUSTMENT AFTER NEGO - - -  P  48,195.00

                      -------------------------------------------------------------------

FINAL AMOUNT PAID TO ALEX -- - - - - - P 799,200.00

ADD OTHER  EXPENSES - - - - -  - - - - - P 149,238.00

                      -------------------------------------------------------------------


TOTAL COST for the 3-room Building - P 948,438.00

Details of the contact amount with Alex and the additional expenses such as chairs and markers are below for your reference.

I will be submitting to the forum details of the donations and balance of fund available for future projects.

Thank you all for your unconditional support to CITAA. We cannot thank you enough.

Charlie

xxxxxxxx

Project : PROPOSED ONE-STOREY THREE-CLASSROOM SCHOOL BUILDING

( 7 x 7m. CL)

Location : CANTAO-AN, NAGA CITY , CEBU

Owner/Donor : ENGR. CHARLIE NG / CIT ALUMNI ASSOCIATION

Subject : COST ESTIMATES SUMMARY (Simplified Form)

School Building Cost -------------------------------------------------------- 860,334.00

Less : Local Government Counterpart ------------------------------
---   200,000.00

              PhP 660,334.00

Less : Plumbing Fixture ------------ 2,845.00

Plywood Wall Partition ------------ 12,600.00     ---------------------------------        15,445.00

              PhP 644,889.00

Add: Comfort Rooms' Tileworks -----------   20,520.00

Plumbing Works -----------------------              51,395.00

Electrical Works -----------------------               34,240.00

Plywood Folded Partition ------------             29,500.00 ----------------------------- 135,655.00

GRAND TOTAL BUILDING COST --------------------                             PhP 780,544.00

Prepared / Submitted:

Alexander F. Du, D.M.D.

Manager

A.D. Gen. Msdg. & Construction

xxxxxxxx

Additional expenses for Cantao-an:

Teacher's table  ===========                            P 3,000.00
Flowers =================                             2,000.00
school markers ===========                              25,000.00
Snacks(c/oPrincipal)========                                6,000.00
additional jalousie ==========                                  138.00
Rodel Cabigon's service fee===                                 8,100.00
student's chair ============                             105,000.00

 total============================        149,238.00

 

 


Copyright © 2005 Kona Visayan Club.  All Rights Reserved.
All material on this site is the exclusive property of Kona Visayan Club.
This website is maintained by Ruth Zetzsche. Email
ruth@konavisayanclub.org for comments.